Released on August 14, 2020
When using fixed duration, fixed work or fixed units in hammock tasks, the duration of calculated hammock tasks could exceed the end date of the latest child task.
The list implemented in previous beta version has been reduced. It now has only 3 items:
Handling of “fixed work” or “fixed units” here has no real meaning because theses modes are intended to calculated the duration of the task. The duration of a hammock task is defined by its children so these modes have been removed from the list.